Kuhio Highway Emergency Repairs schedule as of Nov 2018
Task |
Description |
Est. Completion |
Embankment Repair |
|
|
-Slide A |
Slope mitigation site with tecco mesh above road. |
Mid-January 2019 |
-Slide B |
Slope mitigation site with tecco mesh above road. |
Late November 2018 |
-Site 5 |
Road washout area at mile marker 6.5. |
Early January 2019. Paving, guardrail, and revetment foot remains as of Nov. 5. |
-Site 8 |
Road washout area at mile marker 4.5. |
Early January 2019. Paving, guardrail, staining and installation of revetment foot remains as of Nov. 5. |
Roadway Repair |
Drainage improvements, paving, and guardrail installation at sites 3 and 4. |
|