Kuhio Highway Emergency Repairs schedule as of Nov 2018

Task Description Est. Completion
Embankment Repair    
-Slide A Slope mitigation site with tecco mesh above road. Mid-January 2019
-Slide B Slope mitigation site with tecco mesh above road. Late November 2018
-Site 5 Road washout area at mile marker 6.5. Early January 2019. Paving, guardrail, and revetment foot remains as of Nov. 5.
-Site 8 Road washout area at mile marker 4.5. Early January 2019. Paving, guardrail, staining and installation of revetment foot remains as of Nov. 5.
Roadway Repair Drainage improvements, paving, and guardrail installation at sites 3 and 4.