Updated: Kamehameha Highway paving work continues on Monday, Sept. 23
Posted on Sep 23, 2024 in Highways News, Main, NewsUPDATE 9/26/24:
HONOLULU – The Hawai‘i Department of Transportation (HDOT) notifies drivers that the Kamehameha Highway Repaving at Likelike Highway will continue in Kāneʻohe across from Servco Toyota Monday, Sept. 23.
Crews will be working between 8:30 a.m. and 2:30 p.m. on the following. Bold indicates the primary closure scheduled for that day. All other closures are for work zone safety or to facilitate construction. HPD to direct traffic.
Work has been adjusted due to field conditions.
| Monday, Sept. 23 |
|
| Tuesday, Sept. 24 |
|
| Wednesday, Sept. 25 |
|
| Thursday, Sept. 26 |
|
| Friday, Sept. 27 |
|
The Kamehameha Highway paving project between Pali Highway and Likelike Highway ends at the state right of way on Kamehameha Highway fronting Servco Toyota.
This segment of the project is estimated to be finished on Oct. 8.
The paving portion of this project is estimated to be done by mid-October, then crews will work on raising/lowering manholes and putting down permanent striping.
For a list of weekly lane closures go here: https://hidot.hawaii.gov/highways/roadwork/oahu/
Mahalo for your patience as we improve the roadway.
###