Keaau-Pahoa Road Shoulder Lane Conversion, Phase 2, Shower Drive Intersection Improvements
UPDATE ON KEAAU-PAHOA ROAD SHOULDER LANE CONVERSION, PHASE 2, SHOWER DRIVE INTERSECTION IMPROVEMENTS
MAY 8, 2017
The Hawaii Department of Transportation (HDOT) provides the following update on the Keaau-Pahoa Road Shoulder Lane Conversion, Phase 2, Shower Drive Intersection Improvements project. Work has temporarily been stopped and is anticipated to resume in early June.
Construction has been temporarily stopped as HDOT is in the process of obtaining a new permit for this project which is designed to improve traffic flow in Puna through the installation of a permanent north bound shoulder lane and a temporary south bound shoulder lane between mile posts 4.15 and 4.25 of Keaau-Pahoa Road (Highway 130) and installation of a traffic signal at the Keaau-Pahoa Road/Shower Drive intersection. The Keaau-Pahoa Road Shoulder Lane Conversion, Phase 2, Shower Drive Intersection Improvements project also involves relocation of water system facilities and utility poles as well as installation of pavement markings, striping, and signage.
The contractor for Phase 2 began work in January 2017 using a permit that was obtained for Phase 1 of the shoulder lane conversion project. This permit expired during the Phase 2 construction. HDOT anticipates receiving the new permit within 40 days and is revising the estimated completion date for this project to mid-November.
Further updates will be available on the HDOT Highways Division website (https://hidot.hawaii.gov/highways/) under the Major Projects tab.