Single lane closure for work on Mākaha Bridge No. 3, extended through March 22

Posted on Jan 25, 2024 in Highways Posts, Main, News

HONOLULU– The Hawaiʻi Department of Transportation (HDOT) issues this update for continued work on the Mākaha Bridge Replacement Project No. 3 and 3A. 

There will be an extension of the 24-hour, single-lane closure on Farrington Highway (Route 93) at Mākaha Bridge No. 3, (the bridge southeast of Kili Drive), through Friday, March 22. The closure is required for the completion of bridge approaches to the permanent steel structure for each bridge. This is a 24-hour closure that includes weekends and holidays.  

Traffic in both directions will be maintained through the remaining open lane using alternating traffic control. Flaggers and special duty police officers will be on-site to assist with traffic control and safety procedures. Access to Mākaha Beach Park, Kea‘au Beach Park, Mākua Beach Park and Keawa‘ula Beach/Yokohama Bay will be available during the closure. 

First responders have been notified and will be allowed access through the work zone during the closure period. In the event of a red-flag warning, or natural disaster warning during closure hours, HDOT will implement safety measures to protect the public.  

There will be no closures on the weekend of Saturday, Feb. 17 to Monday, Feb. 19 and Saturday, Feb. 25 to Sunday, Feb. 26 for the Buffalo Big Board Surfing Classic at Mākaha Beach. Details: https://hoomaa.org/buffalo-big-board-surfing 

This work, which was previously stated to finish on Friday, Jan. 26, was extended due to construction supply delays and inclement weather resulting in 18 unworkable days. Mākaha Bridge 3A was completed on Friday, Jan. 12 and will remain open during this closure. 

Remaining work for this project includes the installation of permanent power poles by HECO, and completion of stone slope walls, also called riprap, at Mākaha Bridge 3. The anticipated completion date of the overall project is May 2024. 

For up-to-date closure information, call the HDOT, Public Affairs Office at 808-587-2160. For project information and a map of the work area, please click here: https://hidot.hawaii.gov/highways/makaha-bridge-replacement-project-no-3-and-no-3a/  

Motorists are advised to plan accordingly, allow for extra travel time to get to their destinations and proceed with caution through any work areas. 

Electronic message boards will be posted with closure information. Please note all work is weather permitting. The final completion date of this project is subject to change per these conditions. 

HDOT thanks the public for its cooperation as we work to maintain safe facilities. 

 

 

###