Kuhio Highway Emergency Repairs Status as of September 2018
Project Status (as of 9/11/18) – View the table below for a list of HDOT repair projects and current progress. The current estimate for completion of the emergency repairs to Route 560 is the end of 2018.
# | Location | Description of work | Progress |
Haena to Hanalei | |||
1 | Route 650, MP 10 at Kee State Park | Reconstruct roadway. | Design in progress. |
2 | Route 560, MP 9.55 at Limahuli Stream Crossing | Repair concrete section lost in flooding. Resurface ford crossing. | Design in progress. |
3 | Route 560, MP 8.7 at Haena Beach Park | Repair roadway shoulder. | Design in progress. |
4 | Route 560, MP 8.76 at Manoa Stream Ford Crossing near Haena Beach Park | Repair entire crossing. | Design in progress. |
5 | Route 560, MP 6.5 Repair Site 2 (road washout area) | Roadway stabilization area with single lane remaining. Debris removal, slope wall installation including soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair. | Prepping reinforcing for first shotcrete application of final layer. Prepping for final aggregate base course fill on top of wall. |
6 | Route 560, 15 or more locations between MP 6.5 and 4.4 (Land slide zones) | Debris removal, slope scaling, slope stabilization, guardrail replacements, pavement repairs. | Majority of debris removal and slope scaling complete. Contract awarded and work initiated for slope stabilization of two most critical slopes (Slides A & B). |
Slides A & B | Slope scaling and reinforcement. | Completing construction of access to shape slope to accommodate tecco mesh reinforcing. | |
Route 560, MP 6.3 Repair Site 3 | Roadway stabilization area. Debris removal, slope wall installation including soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair. | Soil nail installation complete. Prepping for installation of reinforcing. | |
Route 560, MP 6.2 Repair Site 4 | Roadway stabilization area. Debris removal, slope wall installation including soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair. | Installing soil nails. | |
Route 560, Repair Site 5 | Slope reinforcement. | Scheduled for soil nail installation after Site 6. | |
Route 560, Repair Site 6 | Slope reinforcement | Soil nail installation complete. Installing reinforcing in preparation for shotcrete. | |
7 | Route 560, MP 5.8 | Lumahai Stockpile area | Stockpiles will be utilized and maintained to support the work as it progresses, and will be closed out upon completion of the work. |
8 | Route 560, MP 4.5 Repair Site 1 (road washout area) | Roadway stabilization area. Debris removal, slope wall installation including soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair | Final shotcrete wall sculpted. Ready for final aggregate base course fill on top of wall. Prepping for scour wall at toe. |
9 | Route 560, MP 4.4 | Waikoko Stockpile area | Stockpiles will be utilized and maintained to support the work as it progresses, and will be closed out upon completion of the work. |
10 | Waikoko Bridge | Replace existing bridge | Awaiting execution of Section 106 Memorandum of Agreement. |
11 | Waipa Bridge | Replace existing bridge | Awaiting execution of Section 106 Memorandum of Agreement. |
12 | Route 560, MP 3.7 | Staging area | Staging area currently in use. |
13 | Waioli Bridge | Rehabilitate existing bridge, remove debris from under bridge | Awaiting execution of Section 106 Memorandum of Agreement. |
14 | Route 560, MP 1 | Debris removal, slope scaling, guardrail replacements, minor pavement repair (April). Slope stabilization (Lane). | Repairs from April Flood had been completed. Currently preparing scope of work from Lane damages. |
15 | Route 560, MP 0.5, near Hanalei Bridge | Debris removal and slope clean-up | Complete |
Kalihiwai | |||
16 | Route 56, MP 25 | Debris removal, slope scaling | Complete |
17 | Route 56, MP 24.9 | Debris removal from under bridge, CRM wall replacement | Debris removal complete. CRM wall in design. |
Wailua | |||
18 | Wailua Bridge | Debris removal from river under bridge (April). Adding scour protection post Lane. | Debris removal complete. Scour protection measures in design. |