H-1 & H-201 Projects Quick Information

Project Name Typical Work Schedule Estimated Completion Date* 
H-1 Salt Lake Rehabilitation Continuous Weekend Closure, Eastbound, 3 right lanes:
Friday from 6:30 p.m. to Monday 2 a.m. 

Fourth right lane closure, Eastbound:
Friday, 7 p.m. – Saturday, 4:30 a.m. 
Saturday, 7 p.m. – Sunday, 7 a.m.


Weeknight (Monday -Thursday) to be scheduled for striping work, TBA 
February 2026
H-1 Pearl City and Waimalu Viaduct Improvements between the Hālawa Interchange and the H-1/H-2 split Nightly: Monday – Friday 7 p.m. – 4:30 a.m. the following day

Weekend work:
Friday from 7 p.m. – 6 a.m. Saturday 
Saturday from 7 p.m. – 8 a.m. Sunday   
March 2027 
H-201 Moanalua Freeway Paving between the H-3 Freeway ramp and the Fort Shafter overpass 

Nightly 3 left lane closure Sunday 9 p.m. – Friday 5 a.m.

Switching to 3 right lanes, week of 2/9/26

Sundays, 8p.m. – 5:30 a.m. 

Monday – Friday 
9 p.m. – 5:30 a.m. the following day 

July 2026 
H-1 Eastbound Improvements – Ola Lane to Likelike Highway 24/7 Closures:
– H-1 eastbound right shoulder near Ola Lane overpass
– Beckley St. at Gulick Avenue 
– H-1 westbound right shoulder near the Likelike Hwy. on-ramp and the Gulick Ave. overpass

Nightly (when needed), Monday – Friday, 9 p.m. – 4:30 a.m. the following day, full closures of H-201 Moanalua Fwy. on-ramp to support this closure


Daily alternating single lane closures on Gulick Avenue Overpass and Richard Lane, 
Monday – Friday, 8:30 a.m. – 5 p.m. 

Daily full closures of Beckley Street, Monday – Friday, 7 a.m. – 3:30 p.m.   
October 2027 
*Please note all work is weather permitting. The final completion date of any project is subject to change per these conditions.

More Roadwork Resources:

To view the weekly roadwork lists, please visit: https://hidot.hawaii.gov/highways/roadwork.

To sign up for weekly HDOT lane closure updates please visit: https://public.govdelivery.com/accounts/hidot/subscriber/new